| 
			
				| 
					
						| Project Log:  Thursday, February 3, 2011 
 With half a day at my disposal, I pressed onwards with 
						the preliminary aspects of the tank installations.
 
 Yesterday's tabbing had cured overnight, so I did the 
						usual quick sanding to relieve rough edges and prepare 
						the surfaces for future work; this wrapped up the key 
						structural work required for the engine room tankage 
						spaces.  While there'd be additional construction 
						to enclose the tanks, I planned on this rigged "base" to 
						be the main means of restraint for the tanks.
 |  
						| 
    |  
						| I reinstalled the forward (fuel) tank on each side, 
						holding them in place with some foam scraps.  Then, 
						I fitted the after (water) tank in the space remaining 
						on each side, following the same general layout process 
						I'd used earlier on the fuel tanks to locate and drill 
						holes for the water tank drains.
 
 For various reasons, even though the two tanks on each 
						side were designed as continuations of one another 
						(essentially designed as one large tank that was cut in 
						half) and therefore should have lined up perfectly, the 
						water tanks, when placed in position, ended up about 
						1/2" - 1" higher than the fuel tanks just ahead.
 
 Though this bothered me on some level--I'd have 
						preferred it if the tanks were level with one another as 
						designed--it didn't bother me enough to consider 
						adjusting the forward tanks' positions to raise them 
						even with the aft tanks:  this seemed entirely 
						unnecessary to satisfy vanity in a space that wouldn't 
						even be seen later, and would have meant a lot of 
						additional work, since it would mean the forward tank no 
						longer rested on the hull, but would require some sort 
						of support system.  And there was no practical 
						reason whatsoever why this slight misalignment made any 
						difference to the tanks' function or security.
 
 Otherwise, the tanks fit the space as designed, and 
						tightly against the bulkheads on three sides.  I'd 
						fill the voids between the hull and the angled tanks 
						sides with expanding foam a bit later, once I'd 
						finalized all the other installation details.
 |  
						| 
    
 
    |  
						| I was awaiting the pipe nipples and shutoff valves for 
						the tanks, which were due anytime, and until those were 
						installed in the drain fittings, I'd not proceed further 
						with the tank installation-though for all intents and 
						purposes the main installation work was complete, at 
						least in terms of the significant structure required to 
						retain the tanks securely.
 
 Next on the agenda was the aft fuel tank.  I 
						brought the new plywood platform up to the boat and 
						test-fit it in its designated space beneath the cockpit.  
						Once I'd aligned it properly, I made some reference 
						marks on the hull showing the edges of the platform and 
						also a rough indication of where I needed to apply paint 
						before its installation.
 |  
						| 
  |  
						| With the platform removed to the bench, I coated the 
						bottom side and edges with epoxy resin, as this portion 
						of the platform would be inaccessible once it was 
						installed.
 |  
						| 
  |  
						| Inside the boat, I applied a coat of gray Bilgekote 
						paint to the area that would soon be hidden by the new 
						tank platform, including the depths of the bilge 
						beneath.
 |  
						| 
  
 |  
						| Total Time Today:  4.25 hours
 |  
						| < 
						Previous | Next >
 |  |  |