| 
			
				| 
					
						| Project Log:  Saturday, December 3, 2011 
 Beginning where I left off last weekend, I installed the 
						three deck fill/vent fittings in the port recess, 
						securing them with sealant and screws.
 |  
						| 
  |  
						| A reader brought up a concern about the fill cap labels 
						and the possibility of mistaking the water fill for 
						diesel, or vise versa.  Although the 
						readily-identifiable caps were attached to the fills 
						with small chains in the usual way, the bodies of the 
						fills themselves were not labeled--just the caps--and 
						because of the proximity of the different fills on each 
						side of the boat (plus the fact that the cap labels were 
						just appliqués and potentially impermanent), I felt this 
						was a valid point, so I had some tank tags made up to 
						clearly mark each fill, cap on or cap off.  The 
						tags were self-adhesive, but I thought I might add some 
						tiny screws to ensure they also remained in place.
 |  
						| 
  |  
						| To aid in the eventual layout and construction of the 
						longitudinal pilothouse bulkheads, I temporarily 
						installed the tank fill unit assemblies; I wouldn't 
						permanently install these till the boat was painted, but 
						for now I wanted them in place to help me locate various 
						openings and, eventually, other installations that would 
						go in the adjacent spaces.
 |  
						| 
    
 
    |  
						| My work on the pilothouse interior was temporarily 
						stymied as I was finally forced to admit that I couldn't 
						proceed till the engine--and, most importantly, the 
						remote coolant header tank--arrived at the shop.  
						I'd learned that as of last week, the engine had arrived 
						at the North Carolina distributor, so I sent off my 
						final payment and hoped to have the engine in hand in 
						the near future.
 
 The header tank was critical because it needed to be 
						mounted somewhere above the domestic water heater, and 
						this meant somewhere in the pilothouse behind the new 
						side panels.  I didn't know the dimensions of the 
						tank, and most other aspects of the new construction 
						hinged upon its ultimate location, so without it I found 
						myself at a standstill.  Anxious as I was to 
						continue with the interior construction, I made myself 
						refocus my attention to some other part of the project; 
						certainly there was no shortage of other tasks I could 
						work on in the meantime.
 
 After some delay, late last week I received four large 
						boxes containing all the pieces and parts required for 
						the diesel heating system.  One thing I'd already 
						learned was that there was no "stock" kit containing 
						everything needed, since each installation was so 
						potentially different, so despite careful planning I 
						wouldn't know till I installed everything whether I'd 
						ordered all the correct parts or not.
 
 In any event, I thought it prudent to check that I'd 
						received everything I ordered, as well as get some sense 
						of all the pieces in 3D, so I unpacked everything and 
						marked it off my list in turn.  The large pile was 
						more than slightly daunting in scope and complexity, 
						but, like the larger scope of the boat project itself, 
						would surely be easier to cope with with item by item, 
						system by system, rather than as a whole.
 
 (Not shown:  the system water hose)
 |  
						| 
    |  
						| The good news was that the Webasto TSL-17 diesel boiler 
						was quite a bit smaller than I'd anticipated, which 
						meant it'd be an easy--luxurious, even--fit in the space 
						I'd planned for it in the engine room.
 |  
						| 
  |  
						| During my planning and ordering process, I'd had various 
						discussions with the supplier, and one of the things 
						that came up was that they recommended that the boiler 
						use its own dedicated fuel pickup rather than drawing 
						off an existing fuel line or manifold, this to avoid the 
						possibility of competing fuel supply needs affecting the 
						operation of either the boiler or main engine.
 
 Since there was no reason I couldn't install an 
						additional fuel pickup in one of the tanks--and in fact 
						doing so would actually make the fuel supply run to the 
						boiler more convenient--I ordered a fuel pickup tube 
						designed for use with the boiler, which I planned to 
						install in the after (center) fuel tank.
 
 While having the dedicated pickup meant that I'd only be 
						able to draw fuel from the one tank, I felt that this 
						was a small compromise.  I chose the center tank 
						because I expected this would be the last tank I'd 
						select for engine use, assuming all three diesel tanks 
						were filled, so it seemed most likely there'd always be 
						substantial fuel in this tank under any circumstances.  
						Now was the time to install this new supply pickup in 
						the tank.
 |  
						| 
  |  
						| Installation would be a simple matter of drilling and 
						tapping the appropriate-sized hole and threads in the 
						polyethylene tank; the wall thickness (3/8") was more 
						than enough to provide adequate threads for the supplied 
						fitting without a need for a bushing or other fiting.  
						However, there wasn't enough clearance above the top of 
						the tank to drill and tap the hole, and insert the 
						fitting, so I unstrapped the tank and slid it forward 
						into the engine room for better access.
 
 In short order, I drilled and tapped the new hole 
						(3/8-24 threads) and installed the new pickup, along 
						with a shutoff valve I'd ordered as part of the heater 
						installation.
 |  
						| 
  |  
						| While the tank was out, I installed all the other 
						fittings, which I'd recently ordered with this 
						intention:  fill, vent, supply, and return.  
						Afterwards, I returned the tank to its platform and 
						resecured it.
 |  
						| 
    |  
						| Similarly, I took the opportunity to install the tank 
						fittings on the other four tanks outboard of the engine 
						room.  The access was as good as it would ever be, 
						and with any luck I'd soon be installing portions of the 
						related fuel and water systems, so this was a good way 
						to spend the afternoon, and in any event was one of 
						those seemingly insignificant tasks that not only needed 
						to be done, despite it having no apparent--or 
						immediate--impact on the completion of the vessel, but 
						also took a surprisingly long time to do.
 |  
						| 
    |  
						|  |  
						| Total Time Today:  5 hours
 |  
						| < 
						Previous | 
						Next >
 |  |  |