| 
			
				| 
					
						| Project Log:  Saturday, July 7, 2012 
 I spent part of the morning on some final mast paint 
						preparations, moving the masts across the yard away from 
						the building, masking the remaining hardware, and 
						preparing the paint and other materials.  It still 
						looked like a good weather window coming up, and I was 
						looking forward to completing this job.  At the end 
						of the day, I covered both spars with polyethylene 
						tubing to help keep dew from settling on them, as my 
						first step before painting would be to sand once more, 
						and I wanted to get started early.
 
 From storage, I dug out the spreader tube from the 
						mizzen mast and cleaned it up and sanded it so I could 
						paint that (along with the new mainmast spreaders) at 
						the same time.
 |  
						| 
    |  
						| Back up in the boat, I started work on the final hoses 
						required for the engine heat exchanger's connection to 
						the water heater and coolant tank.  At first 
						glance, this was a simple chore, but as I prepared to 
						lead a hose from the engine room to the remote coolant 
						tank above, I realized that I had better figure out some 
						other hose runs first--most notably the fuel fill hose 
						that had to lead from the same compartment back to the 
						aft centerline fuel tank.
 
 Since the fuel fill hose was larger and stiffer, places 
						where I could run it through this increasingly 
						complicated little area were limited.  The best 
						place was inboard of the water heater, but to run it 
						there I needed to use a hole saw to cut partially 
						through the plywood support for the water heater, as 
						this was limiting the space available for the hose.  
						Fortunately, this went easily, and after installing some 
						chafe gear on the fuel hose I led it through and 
						connected it to the tank, leaving the other end long 
						pending final installation of the fuel fill panel in the 
						side of the pilothouse.
 |  
						| 
    |  
						| While I was at it, I led the vent line for this tank 
						through the same general area, securing it along the  
						way as needed and leaving the forward end long for now.
 |  
						| 
    |  
						| Now I could run the two 5/8" hoses required for the 
						engine's coolant tank.  The first hose led from the 
						bottom of the slim green heat exchanger (part of the 
						heating system), where I'd previously installed a hose 
						stub and valve, and then the return line from the 
						coolant tank ran back to the engine itself, to the 
						second of two fittings installed for this purpose.
 
 |  
						| 
      
 
    |  
						| Finally, I pulled the air intake hose for the diesel 
						boiler out of its box and checked to see how I could 
						lead it to the connection on the boiler.  I found I 
						could lead it behind the support where I installed the 
						fuel filter and valve for the boiler, and this meant the 
						intake wouldn't interfere with the rubber hose leading 
						the boiler nearby.  I'd been waiting to install a 
						service valve in this length of hose till I could 
						determine it wouldn't interfere with the air intake, but 
						with that question resolved I cut the hose and installed 
						an inline shutoff valve, which I secured just above the 
						fuel lines below.  This valve, along with another 
						one in the system on the other side of the circulation 
						pump, would allow the boiler or pump to be removed from 
						the system if needed without having to drain the entire 
						system.
 |  
						| 
    |  
						|  |  
						| Total Time Today:  5.75 hours
 |  
						| < 
						Previous | Next >
 |  |  |