| 
			
				| 
					
						| Project Log:  Saturday, October 26, 2013 
 I surprised myself by wrapping up the masking and 
						high-build primer prep (at least for the initial areas 
						to be so treated) in less time than expected--good news, 
						but the reality was that I'd hoped to be at this point 
						in the process about three months earlier, which just 
						didn't happen thanks to various other commitments and 
						demands on my time.
 
 In the event, picked up where I left off, and completed 
						the masking work on the starboard sidedeck, where I 
						covered the bulwarks and decks with paper to protect 
						them against overspray from the coachroof and pilothouse 
						painting.
 
 |  
						| 
      |  
						| Access-wise, I'd also be able to include the forward 
						bulwarks in this first round of painting, so I masked 
						around those areas accordingly.  My plan was to 
						include direct sidedeck access on each side of the boat 
						(via ladders), so I could climb aboard into the 
						masked-off sidedecks and spray the coachroof and 
						pilothouse on each side of the boat; I'd also be able to 
						reach the foredeck area under this approach.
 |  
						| 
      |  
						| Next, I installed plastic over the cockpit, taping it to 
						the previously-masked lines I'd installed around the 
						perimeters.  this left most of the coamings exposed 
						for painting in this round.  The actual cockpit, 
						and aft end of the pilothouse, would get addressed 
						sometime later, after I'd completed the paint work on 
						all other areas of the deck an hull.  This was to 
						give me ample time (and hopefully inclination) to 
						finally address the structural changes to the cockpit, 
						which a recent review of the project logs showed I'd 
						been whining about consistently for years (while 
						continuing to ignore the actual work).
 |  
						| 
 
    |  
						| To allow myself access to the cockpit coamings for 
						spraying, I set up two sections of staging around the 
						stern, and set up two ladders--one on each side--that 
						would give me access to the decks for spraying those 
						areas, as well as direct access to the pilothouse roof 
						if needed.  Meanwhile, I draped the topsides with 
						sheet plastic to protect them during the deck painting 
						exercises.
 
 |  
						| 
      
 
      |  
						| Finally, I solvent-washed the exposed deck areas with 
						the paint system's proprietary solvent and settled in to 
						wait till I could paint.  I'd created a quandary 
						for myself in that with the day's unexpected efficiency 
						I'd forced a week-long delay in the process.  I 
						needed two consecutive days in order to apply and sand 
						the paint, since I always liked to sand as soon as 
						possible after application while the paint was still 
						relatively soft (as with all epoxies, the primers 
						continued curing and became harder over time).  So 
						I'd have to wait till the next weekend in order to allow 
						myself the time required.
 
 This would be a continuing need (and frustration) 
						throughout what was to be a very drawn-out painting 
						process--while the end result would ultimately be 
						satisfying, and a huge checkmark on the list, it was a 
						process to be endured rather than enjoyed.
 
 Basically, this was how I envisioned the process for the 
						decks in the weeks ahead:
 
 1.  Spray and sand high-build primer (3 coats) on 
						phase 1 areas--coachroof and pilothouse [2 days]
 
 2.  Spot and pinhole filling/sanding as needed [1 
						day]
 
 3.  Spray and sand finish primer (3 coats) on 
						coachroof and pilothouse [2 days]
 
 4.  Unmask phase 1 areas; blend parting line; and 
						remask/final prep for phase 2 (sidedecks, bulwarks, and 
						cabin sides) [2 days]
 
 5.  Spray and sand high-build primer (3 coats) on 
						phase 2 areas [2 days]
 
 6.  Spot and pinhole filling/sanding as needed [1 
						day]
 
 7.  Spray and sand finish primer (3 coats) on phase 
						2 areas [2 days]
 
 8.  Unmask phase 2 areas; blend parting line; 
						remask deck for topcoats [2 days]
 
 9.  Spray gloss topcoats (3 coats), hopefully on 
						all areas in one session--details still to be worked out  
						[1 day, hopefully]
 
 Onwards and upwards.
 
 |  
						|  |  
						| Total Time Today:  2.75 hours
 |  
						| < 
						Previous | 
						Next >
 |  |  |