| 
			
				| 
					
						| Project Log:  Saturday, March 5, 2011 
 I cheated when I decided not long ago to "end" Phase II 
						of the project and start Phase III.  Technically, I 
						still had two new tanks to install--tankage being of the 
						main focuses of Phase II.  I'd completed everything 
						but the actual installation of the aft center fuel tank 
						beneath the cockpit, constructing and installing a new 
						platform for its support, but had yet to truly address 
						the forward water tank.
 
 Semantics aside, I next wanted to focus on the 
						installation of the forward water tank.  As it 
						turned out, this ended up being quite straightforward.
 
 To begin, I drew a level line across the chainlocker 
						bulkhead, using the shadow of an old support cleat to 
						locate the line; the old cleat had originally held the 
						forward end of the V-berth platform, and to the extent 
						possible I intended to keep the height the same.
 
 From this one reference point, I made a series of marks, 
						more or less level, along the sides of the hull leading 
						aft, simply to give me a visual reference for where the 
						V-berth platform would end up.  I needed to know 
						this so I could ensure that the forward water tank was 
						properly positioned.
 |  
						| 
  |  
						| Of prime importance in the tank's positioning was the 
						fact that  I'd redesigned the tank so that all 
						fittings were on top of the tank, with none entering the 
						sides.  Therefore, I'd need a bit more clearance 
						above the tank top to allow for the fittings, 
						particularly a worst-case scenario for the large fill 
						pipe.  To that end, I temporarily installed an old 
						1-1/2" sweep elbow I had on hand, which represented the 
						most bulky type of fitting I'd conceivably use.
 
 With this fitting installed, I held the tank in place 
						against the hull and leveled it side-to-side and 
						fore-and-aft, then eyeballed the height of the sweep 
						fitting against the height of the mark on the 
						chainlocker bulkhead, confirming that the fitting would 
						be lower than the platform by extending the level 
						forward.  I also allowed space for the hose itself.
 |  
						| 
    |  
						| With the tank loosely held in this position, I made a 
						series of reference marks on the hull so I could 
						reposition it easily.  From beneath, I noted that 
						the edges of the tank bottom more or less contacted the 
						hull along their lengths, which meant I could use the 
						tank bottom as a pattern for a support platform.  
						While most of the weight of the tank could bear along 
						its edges, the plastic tank required additional support 
						beneath to prevent the possibility of distortion, and a 
						basic support platform would achieve this.
 
 With the tank removed to the main cabin, I created the 
						paper pattern.
 |  
						| 
  |  
						| To take advantage of the availability of materials on 
						hand, I decided to build the platform from two laminated 
						layers of 9mm Meranti plywood, giving me a total 
						thickness of 3/4".  Using the pattern, I cut out 
						the first section, adding 1/2" in length at the aft end 
						to provide a place for an after vertical support 
						bulkhead to rest later.
 |  
						| 
  |  
						| I added the same length to the forward end as well, but 
						during my test-fit in the boat I discovered that the 
						platform extended too far forward and wouldn't provide a 
						natural limber for the passage of water beneath, so I 
						made a mark on the new platform to reduce its overall 
						length by about 2" (not shown in these photos).
 |  
						| 
    |  
						| Satisfied with the shape of the platform, I used its 
						bottom edge (the sides were beveled) to pattern the 
						second layer, which I cut out and then epoxied and 
						screwed into position, laminating the two layers 
						together.  I held the bottom layer short of the 
						forward end, partly because that's the width of the 
						plywood I had remaining, and partly because I saw no 
						reason to bother cutting an additional piece for the 
						narrow forward end, which wouldn't require the strength.
 
 Once the lamination was complete, I applied epoxy all 
						over the bottom side and edges of the platform.
 |  
						| 
  |  
						| Before installing the platform in the boat, I applied a 
						coat of gray bilge paint to the space beneath, leaving 
						unpainted the bonding area near the platform itself.
 |  
						| 
  |  
						| I installed the platform with epoxy around its edges, 
						and created a small fillet between the platform and the 
						hull.  Once the fillet had partially cured, I 
						installed 6" tabbing along the edges to bond the 
						platform securely to the boat, and coated the center 
						part of the plywood platform with epoxy.
 |  
						| 
    |  
						| Moving to the engine room, I vacuumed and solvent-washed 
						the fuel tank platform and adjacent areas.  The 
						epoxy securing the platform had had plenty of cure time, 
						so it was time to paint out this area, the only task 
						standing before the final installation of this tank.
 
 I applied a coat of gray paint over most of the area, 
						leaving a section on the port side aft of the saddle 
						tanks there, where I thought I might be building a 
						platform for a water heater, or storage shelves, or 
						something.  Access and available space in that area 
						was good, which is why I thought it'd be a good location 
						for something.
 
 The starboard side was laid out differently, with the 
						closed-off propane locker (original) above, and I didn't 
						anticipate any installations here, so I painted all the 
						way to, and including, the aft end of the starboard 
						saddle tank bulkhead.
 |  
						| 
      |  
						|  |  
						| Total Time Today:  3.75 hours
 |  
						| < 
						Previous | 
						Next >
 |  |  |