| 
			
				| 
					
						| Project Log:  Sunday, December 30, 2012 
 Now that the templates for the forward cabin overhead 
						were complete, my next step was to transfer them to 
						marine plywood and cut out the two pieces required.  
						I test-fit both pieces, and was generally pleased with 
						the fit; the gap at the forward edge of each piece where 
						they met the boat's centerline was larger than I liked, 
						but the panels were unsupported there and the gap shrunk 
						when I pressed the panels upward, so I planned to add a 
						support cleat there so I could better secure the panels 
						during final installation.  Other minor gaps at the 
						edges would later be covered with trim.
 |  
						| 
    |  
						| I wasn't sure how the final trim around the opening 
						hatch would be configured, but the molded opening 
						beneath the hatch itself was much larger than it needed 
						to be, and I knew there'd be significant trim here, as 
						well as to extend up to the hatch itself.  The new 
						overhead extended as far out as the edges of my support 
						cleats, which I'd placed right at the edge of the 
						oversized molded opening.  Originally, there'd been 
						a massive molded, gelcoated thing that had covered this 
						area from inside, but I'd no plans to reuse that.  
						So for now, I'd just made a 45° angle cut at each corner 
						of the overhead, which I might cut back later depending 
						on final details.
 |  
						| 
    |  
						| The last remaining sections of overhead were in the 
						pilothouse.  Before I could begin templating, I had 
						to cut through the support cleats in several areas to 
						allow passage of various wires (VHF antenna, overhead 
						lights) through the overhead; I'd done the same thing 
						down in the main cabin before.  Earlier, I'd 
						installed wire tie mounts in the desired route 
						locations, so it was a straightforward matter to remove 
						small sections of the cleats in way of the wire runs 
						before stringing the wires accordingly.
 |  
						| 
  
 |  
						| At the forward corners, a few wires would have to pass 
						through the pilothouse roof to reach their intended 
						destinations:  sidelights, and a pair of GPS 
						antennas (one for the main system, the other for the AIS 
						unit).  So I figured out where I wanted these to 
						go, and drilled the holes through the pilothouse roof so 
						I could get the wires out of the way for the moment, and 
						so that when it was time to install the overhead I'd be 
						ready.  I'd come back later and treat the raw holes 
						properly with epoxy to seal the core, but for now I'd 
						done what I needed to.
 |  
						| 
    |  
						| For the remainder of the day, I worked on the overhead 
						templates.  I planned to build the overhead in four 
						sections for convenience and ease of installation, 
						having learned well my lessons from earlier sections.  
						To this end, I planned ahead and allowed for the panels' 
						seam on one of the transverse support cleats, so I'd end 
						up with four separate templates built in place.  I 
						completed the two after sections, leaving the forward 
						sections for next time.
 |  
						| 
      |  
						|  |  
						| Total Time Today:  3.75 hours
 |  
						| < 
						Previous | 
						Next >
 |  |  |