| 
			
				| 
					
						| Project Log:  Tuesday, May 12, 2015 
 The three old Barient #10 winches I'd selected for the 
						main and mizzen mast halyards were good solid winches, 
						but had suffered from years of poor maintenance.  
						The net result was that the pawls and bearings were 
						caked with heavy grease, affecting the function of these 
						winches.  I'd first noticed the problem when I 
						installed one of the winches on the mizzen mast, but the 
						other two were in similar condition.
 
 |  
						| 
  |  
						| Starting with the mizzen winch, I removed the works from 
						the mast (leaving the base in place) and cleaned the 
						pawls and bearings thoroughly, and removed the heavy 
						grease from all areas.  I found that the two top 
						pawl springs were either missing or damaged, so I 
						pirated a fourth copy of the winch that I had on hand to 
						steal its pawl springs, since I didn't have any spares 
						on hand.  Afterwards, I lightly greased the shaft 
						and bearings, and reassembled the winch, which now 
						worked well.
 
 Meanwhile, I soaked the other two winch bases and their 
						parts in solvent, then cleaned these up and regreased 
						them appropriately.
 |  
						| 
      |  
						| The original mainmast setup had a pair of 
						slightly-raised bases for the winches, which were in 
						good condition and could accommodate the "new" winches.  
						The design allowed (required, actually) the winches be 
						installed first, before the base was installed on the 
						mast, so I prepared the bases by reinstalling the 
						phenolic cover places with new fasteners, then marked, 
						drilled, and tapped for the new winch bases before 
						bolting them in place.
 |  
						| 
      
 
      |  
						| Continuing mast work, I set up and installed the main 
						control line for the lazy jacks, the bare minimum 
						required before the mast could be stepped.  I hoped 
						to do more layout later, but at least the main lines 
						were in place and ready for the next steps.  This 
						control line ran from one side of the mast, through a 
						cheek block above the spreaders, down to an adjustable 
						block on the front of the mast (secured with a line near 
						the gooseneck with a cleat), then back up to the 
						opposite cheek block and down.  The bitter ends of 
						these two lines would eventually form the main leg for 
						the lazy jacks leading to the boom.
 |  
						| 
    |  
						| In other important works, I assembled three new fenders 
						with new lines and Polarfleece covers.
 |  
						| 
  |  
						| To prepare the mast wiring for its entry into the boat 
						once stepped, I drilled a hole in the forward side of 
						the mast, through which to lead the wires.  I'd 
						eventually install a fitting here to accept a flexible 
						conduit (the other end of which would connect to the 
						mating fitting on deck, leading into the junction box).  
						I chose the forward side of the mast because should the 
						mast be converted to a tabernacle in the future, the 
						wiring exit would need to be clear of the tabernacle 
						sides.  I led the wires through, and would continue 
						work here soon.
 |  
						| 
    |  
						| I bunged the old screw holes in the teak cockpit seats, 
						and when the glue had dried I pared off the excess bungs 
						and installed the seats one last time.
 |  
						| 
    
 
    |  
						| Meanwhile, I took care of sundry items, including a 
						wiring issue with the shower sump pump.  When I'd 
						finished its wiring the other day, it wouldn't operate, 
						and I traced the issue to the fact that I'd led its main 
						feed to the wrong breaker in the panel.  After 
						correcting the issue, the pump worked as expected.
 
 In the afternoon, the required cable for the windlass 
						installation arrived, so it looked like I'd be busy with 
						that in the immediate future.  With ample 
						conservatism, I selected 1/0 cable for the job, and to 
						prepare for its installation I took the time to 
						preinstall a number of wire tie holders along the 
						proposed route for the cable so they'd be in place and 
						ready to hold the cable.  I was awaiting various 
						new windlass parts to rebuild the old Ideal windlass, 
						but could begin the main cable installation at once.
 |  
						| 
  |  
						|  |  
						| Total Time Today:  6.25 Hours
 |  
						| < 
						Previous | Next >
 |  |  |